ZhongDe Wastes technology AG: Introduction for DingZhou Waste-to-Energy Project

 

Frankfurt, 9 May 2018

Dingzhou waste-to-energy project is one of the key project of the company. The project is located in Dingzhou TangHe Recycling Economy Industrial Park and covers an area of 100 mu. The total construction costs for the project amount to RMB 268.8 million with daily waste capacity of 600 tons at the first stage and 300 tons reserved for the second stage. The total annual maximum disposal capacity at the first stage amounts to 219,000 tons. The annual power generation capacity is approximate 68.98×106kWh. The project is equipped with 2 sets of 22.3t/h mechanical furnace boilers with daily capacity of 300 tons each and one 9MW condensing air-cooled turbines. The project adopts advanced power generation technology for municipal waste incineration treatment, which is in line with the national policy requirements for energy-saving and emission-reduction, environmental protection and comprehensive utilization of resources.

 

Dingzhou waste-to-energy project will serve “two cities and three counties”, as the waste output from a single city could not meet the requirements for the stable operation for the incineration power plant. Therefore, the project is built in the form of city alliance. The service scope of Dingzhou project includes Dingzhou City, Anguo City, Wangdu County, Tang County and QuYang County. Based upon the daily waste output from the city alliance, Dingzhou project is designed with current waste disposal capacity of 600 tons/day and 900 tons/day in the long term. The project is located on the plain of north China. With flat terrain and good road planning it meets the requirements of the engineering geological conditions for the project construction. Dingzhou project can realize the target of harmless, reducing and resourceful waste disposal and achieve better economic and social benefits, which are not only in line with national energy and environmental protection policies, but also comply with the development plan of Hebei province.

 

At present, about 73% of the EPC project has been completed, including the construction work for the main plant, office building, complex building and other single buildings, all of which have been put into use and the equipment installation has been basically completed. Except for the power access system and the electrical secondary wiring work, the commissioning and defect elimination work have been fully underway.

 

Dingzhou project is expected to realize grid-connection and power generation and to be put into formal commercial operation at the end of June 2018.

 

 

About ZhongDe Group

ZhongDe Group, as one of the leading players in waste-to-energy industry in China, designs constructs, finances and operates waste-to-energy plants, which generate electricity from the incineration of solid municipal and industrial waste. After selling all BOT (Build, Operate and Transfer) projects, ZhongDe Group is acting as an EPC (Engineering, Procurement and Construction) contractor to develop the incineration plants. Apart from this, it is focused on exploring the market in small scale waste-to-energy plants with waste disposal capacities of around 200 - 300 tons per day, which require less investment and have shorter construction periods. Since 1996, ZhongDe Group has installed approximately 200 waste incinerators in 13 provinces throughout China. It will continuously devote itself to the eco-friendly industry in China.

 

Contact

ZhongDe Waste Technology AG

Ying Sun
Messeturm 25th Floor
Friedrich-Ebert-Anlage 49
60308 Frankfurt
Mob.: +49 (0) 69 50956 5656
Fax: +49 (0) 69 50956 5520
Mail: ying.sun@zhongde-ag.de

 

Overview

9 May 2018

ZhongDe Wastes technology AG: Current Status of WuHai Waste-to-Energy Project


Details

9 May 2018

ZhongDe Wastes Technology AG: Introduction for DingZhou Waste-to-Energy Project


Details

28 November 2016

ZhongDe Wastes technology AG: Fast progress of BOT project in Lanzhou led to strongly improved revenues in the third quarter 2016


Details

27 October 2016

ZhongDe Waste Technology AG: New members of the Supervisory Board


Details

30 August 2016

ZhongDe Waste Technology AG: Project in Lanzhou continues progressing rapidly


Details

27 May 2016

ZhongDe Waste Technology AG: Rapid progress of main BOT project in Lanzhou resulted in strong revenue growth


Details

29 April 2016

ZhongDe Group: Improved project progress in 2015 but earnings impacted by extraordinary effects


Details

27 November 2015

Adverse external and internal effects slow down ZhongDe’s project progress


Details

28 August 2015

ZhongDe Waste Technology AG expects improved project progress for the second half of 2015


Details

28 May 2015

ZhongDe Waste Technology AG: Strong revenue increase reflects continuous project progress


Details

29 April 2015

ZhongDe Waste Technology AG: Remarkable project progress led to improved financial performance in 2014


Details

28 November 2014

ZhongDe Waste Technology AG: Strong year-on-year improvement of financial re-sults in the first nine months 2014


Details

28 August 2014

ZhongDe Waste Technology AG: Half-year results show slight recovery year-on-year


Details

28 May 2014

ZhongDe Waste Technology AG: Project progress not reflected in Q1 2014 results


Details

29 April 2014

ZhongDe Waste Technology AG: Successful sale of manufacturing site led to increase in EBIT and net result


Details

23 December 2013

ZhongDe Waste Technology AG signed contract to sell Beijing Miyun manufacturing site


Details

28 November 2013

ZhongDe Waste Technology AG: Weak business development despite increased order backlog


Details

28 August 2013

ZhongDe Waste Technology AG: Improved but still weak financial resultsin H1 2013 despite increased order backlog


Details

28 June 2013

ZhongDe Waste Technology AG signs EPC contract for new energy-from-waste plant in Wuhai


Details

28 May 2013

ZhongDe Waste Technology AG: First quarter 2013 shows improved year-on-year results


Details

29 April 2013

ZhongDe Waste Technology AG: Challenging circumstances adversely affect results 2012


Details

30 November 2012

ZhongDe Waste Technology AG: Financial results benefit from positive one-off effects in the third quarter 2012


Details

23 October 2012

ZhongDe Waste Technology signs BOT contract for largest waste-to-energy plant in China


Details

30 August 2012

ZhongDe Waste Technology AG: Financial results impacted by further project delays


Details

29 August 2012

Changes in the Supervisory Board of ZhongDe Waste Technology AG


Details

31 July 2012

ZhongDe Waste Technology AG: Difficult start into financial year 2012


Details

23 July 2012

Interview with Börsen Radio Network


Details

17 July 2012

ZhongDe Waste Technology AG: Weak 2011 results due to project delays


Details

30 April 2012

ZhongDe Waste Technology AG: Publication of Annual Report 2011 delayed


Details

30 November 2011

ZhongDe Waste Technology AG: Revenues and gross profit improve while EBIT and net profit decline


Details

14 September 2011

ZhongDe Waste Technology AG relocates legal domicile from Hamburg to Frankfurt


Details

31 August 2011

ZhongDe Waste Technology AG: Audited H1 2011 results


Details

31 May 2011

ZhongDe Waste Technology AG: Q1 results show positive trend


Details

26 May 2011
ZhongDe Waste Technology AG: State Council of China strengthens municipal waste treatment industry
Details

20 May 2011

ZhongDe Waste Technology AG: Feicheng BOO project passes emission test


Details

2 May 2011
ZhongDe Waste Technology AG: Strong order backlog, equity and cash position despite slight net loss in 2010
Details

24 February 2011
ZhongDe Waste Technology AG: Final gross profit rate of Datong EPC project of 26.6%
Details

30 December 2010
ZhongDe Waste Technology AG: Completion of Feicheng project construction
Details

30 November 2010
ZhongDe Waste Technology AG: Strong order backlog and cash position despite revenue decrease
Details

19 November 2010
ZhongDe Waste Technology AG: Change in Supervisory Board
Details

10 November 2010
ZhongDe Waste Technology AG signed financial leasing contracts of two BOT projects
Details

30 August 2010
ZhongDe Waste Technology AG: Better Performance of Q2 2010 vs. Q2 2009
Details

27 August 2010
ZhongDe Waste Technology AG: BNY Mellon has been appointed as Depositary Bank for ADR program
Details

19 July 2010
ZhongDe Waste Technology AG moves Offices from Hamburg
to Frankfurt am Main
Details

4 June 2010
ZhongDe Waste Technology AG signs EPC contract with Shouguang Fuyuan Waste to Power Co., Ltd
Details

28 May 2010
ZhongDe Waste Technology AG: Weak Q1 financials due to difficult weather and market conditions
Details

30 April 2010
ZhongDe Waste Technology AG: Strong order backlog after strategic shift
Details

12 February 2010
ZhongDe Waste Technology AG: Successful operation of Datong Project
Details

30 December 2009
ZhongDe Waste Technology AG signs agreement to increase contract amount of Datong Project
Details

30 December 2009
ZhongDe Waste Technology AG signs EPC contract with Dingzhou Ruiquan Solid Waste Treatment Co., Ltd
Details

30 November 2009
ZhongDe Waste Technology AG presents its financial results for Q3 2009
Details

7 September 2009
ZhongDe Waste Technology AG signs Letter of Intent with Covanta Energy Asia Pacific Holdings Ltd.
Details

31 August 2009
ZhongDe Waste Technology AG adjusted strategy for future growth in 2009
Details

3 August 2009
ZhongDe Waste Technology AG Annual General Meeting adopts dividend
Details

30 July 2009
ZhongDe Waste Technology AG signs letter of intent with ThyssenKrupp Xervon Energy
Details

20 July 2009
ZhongDe Waste Technology AG signs contract for waste incineration plant in Zhaodong City
Details

10 June 2009
ZhongDe Waste Technology AG announces to postpone its Annual General Meeting
Details

29 May 2009
ZhongDe Waste Technology AG presents its financial results for Q1 2009
Details

30 April 2009
ZhongDe Waste Technology AG maintains high growth rates
Details

20 April 2009
ZhongDe Waste Technology AG announces signing of two large-size BOT projects
Details

6 April 2009
ZhongDe Waste Technology AG signs Letter of Intent on Renewable Energy Projects for Electricity Generation in Jilin, PRC
Details

3 February 2009
ZhongDe Waste Technology AG announces strategic cooperation agreement with Genesis Energy Holdings Limited
Details

23 January 2009
ZhongDe Waste Technology AG signs contract with Zhucheng Baoyuan New Energy Power Generation Co., Ltd
Details

29 December 2008
ZhongDe Waste Technology AG announces change in the Supervisory Board
Details

28 November 2008
ZhongDe Waste Technology AG reports continued healthy growth in Q3 2008
Details

10 November 2008
ZhongDe Waste Technology AG expects continuous growth and confirms initial estimation for financial year 2008
Details

30 September 2008
ZhongDe Waste Technology AG expects continuous growth and confirms initial estimation for financial year 2008
Details

29 August 2008
ZhongDe Waste Technology AG reports continuous growth in Q2 2008
Details

30 June 2008
ZhongDe Waste Technology AG announces cooperation agreement with Veolia
Details

16 June 2008
ZhongDe Waste Technology AG announces signing of Lianshui BOO project
Details

30 May 2008
ZhongDe Waste Technology AG reports strong growth in Q1 2008
Details

29 April 2008
ZhongDe Waste Technology AG presents its audited full year results for fiscal year 2007: net profit more than doubled – order intake increased by 90% to €44.4 million
Details

7 April 2008
ZhongDe Waste Technology AG announces signing of Xinjiang BOT project
Details

18 March 2008
ZhongDe Waste Technology AG releases preliminary results for fiscal year 2007: net profit more than doubled - order intake increased by 90% to €44.4 million
Details

11 March 2008
ZhongDe Waste Technology AG signs contract for large scale waste incinerator plant
Details

28 November 2007
ZhongDe Waste Technology AG continues to grow in Q3 2007
Details

19 September 2007
ZhongDe Waste Technology AG secures land usage rights in Beijing – headstone for building a second production facility
Details

28 August 2007
ZhongDe Waste Technology AG presents strong performance in H1 2007
Details

9 August 2007
ZhongDe Waste Technology AG announces signing of two BOT projects
Details

12 July 2007
ZhongDe Waste Technology AG: Greenshoe option exercised in full
Details

5 July 2007
ZhongDe Waste Technology AG sets offer price and issue volume
Details

28 June 2007
ZhongDe Waste Technology AG: Price range between Euro 23 and Euro 26
Details

25 June 2007
ZhongDe Waste Technology AG launches its Initial Public Offering on the Prime Standard in Frankfurt
Details

14 June 2007
ZhongDe Waste Technology AG planning IPO in July 2007
Details