Adverse external and internal effects slow down ZhongDe’s project progress
- Revenues of 10.3 million Euros
- EBIT amounts to -4.1 million Euros
- Some projects delayed or suspended, but progress as planned at largest BOT project in Lanzhou
- Year-on-year decrease in revenues and operating result expected for full-year 2015
Frankfurt, 27 November 2015
The first nine months of 2015 were marked by a weaker global economic development and a slow-down in China as well. The tax income of the Chinese Government decreased leading to a higher level of debts of the local governments. Due to these adverse external circumstances as well as due to internal reasons, three BOT projects were delayed and two EPC projects were suspended, which had a negative impact on the nine-month-results of the group.
Revenues went down by 10.3 per cent to 10.3 million Euros (9M 2014: 11.5 million Euros) caused by the slow project progress since the second quarter of 2015. With regard to the business segments of ZhongDe, BOT projects were the main sales driver with revenues of 9.6 million Euros (9M 2014: 5.3 million Euros), while EPC projects accounted for 0.7 million Euros of total revenues (9M 2014: 6.2 million Euros).
Gross profit amounted to -1.4 million Euros (9M 2014: 0.7 million Euros). This decrease was mainly due to the fact that inventories relating to the incinerator segment amounting to 0.9 million Euros had to be written off during 2015. EBIT dropped by 33.3 per cent to -4.1 million Euros (9M 2014: -3.1 million Euros). Net loss increased by 21.9 per cent to -6,7 million Euros (9M 2014: -5.5 million Euros).
Despite the weak nine-month-results, ZhongDe’s equity position remained stable at 113.0 million Euros as at 30 September 2015 (31 December 2014: 112.9 million Euros). The equity ratio amounted to 43.5 per cent (31 December 2014: 45.3 per cent).
Cash and cash equivalents amounted to 81.2 million Euros as at 30 September 2015, a decrease of 6.9 per cent compared to 87.2 million Euros as at 31 December 2014. The largest part of the group’s existing cash is planned to be invested in the construction of the BOT project in Lanzhou, the biggest waste-to-energy project throughout China.
Adjusted outlook due to project delay and suspension
Due to the reasons mentioned above, the completion of the BOT projects in Zhoukou and Xianning had to be postponed to 2016. The Kunming BOT project is expected to be completed in 2017 instead of 2016. The completion of the EPC projects in Zhucheng, Dingzhou and Wuhai will also be delayed. While Zhucheng is assumed to be finalized in 2016, Dingzhou and Wuhai are temporarily suspended until the referring customers signal that the construction can be resumed. However, ZhongDe’s largest project in Lanzhou is progressing according to the original plan.
Considering the delay of some current BOT projects and the suspension of the EPC projects in Dingzhou and Wuhai, the management of ZhongDe was forced to adjust its outlook for the full-year 2015. The total group sales and operating profit for the full-year 2015 are expected to decrease compared to 2014.
Regarding the future development of the company, the management board evaluates all strategic opportunities on a regular basis and will do its best to improve ZhongDe’s profitability and to balance the cash position of the group.
Please find the complete 9M report 2015 of ZhongDe Waste Technology AG on the company’s website under the following link:
http://www.zhongde-ag.com/investor_relations/publikationen.html
About ZhongDe Group
ZhongDe Group designs, invests, constructs, finances and operates energy-from-waste plants generating electricity from the incineration of solid municipal and industrial waste. ZhongDe realizes either EPC (Engineering, Procurement and Construction) or BOT (Build, Operate and Transfer) projects, focusing on large-scale plants with waste disposal capacities of around 1,000 tons per day. Since 1996, ZhongDe Group has installed approximately 200 waste incinerators in 13 provinces throughout China. ZhongDe is one of the leading players in the project development and operation of energy-from-waste plants in China.
Contact
ZhongDe Waste Technology AG
William Jiuhua Wang
Executive Director and CFO
E-Mail: william.jw@zhongdetech.com
Ying Sun
Investor Relations
Messeturm 25th floor
Friedrich-Ebert-Anlage 49
60308 Frankfurt am Main
T: +49 69 50956 5655
F: +49 69 50956 5520
E-Mail: ying.sun@zhongde-ag.de
Kirchhoff Consult AG
Nicole Schüttforth
Investor Relations Consultant
T: +49 40 60 91 86 64
F: +49 40 60 91 86 60
E-Mail: nicole.schuettforth@kirchhoff.de
Overview
28 November 2016
ZhongDe Wastes technology AG: Fast progress of BOT project in Lanzhou led to strongly improved revenues in the third quarter 2016
Details
30 August 2016
ZhongDe Waste Technology AG: Project in Lanzhou continues progressing rapidly
Details
27 May 2016
ZhongDe Waste Technology AG: Rapid progress of main BOT project in Lanzhou resulted in strong revenue growth
Details
29 April 2016
ZhongDe Group: Improved project progress in 2015 but earnings impacted by extraordinary effects
Details
28 August 2015
ZhongDe Waste Technology AG expects improved project progress for the second half of 2015
Details
28 May 2015
ZhongDe Waste Technology AG: Strong revenue increase reflects continuous project progress
Details
29 April 2015
ZhongDe Waste Technology AG: Remarkable project progress led to improved financial performance in 2014
Details
28 November 2014
ZhongDe Waste Technology AG: Strong year-on-year improvement of financial re-sults in the first nine months 2014
Details
28 August 2014
ZhongDe Waste Technology AG: Half-year results show slight recovery year-on-year
Details
29 April 2014
ZhongDe Waste Technology AG: Successful sale of manufacturing site led to increase in EBIT and net result
Details
23 December 2013
ZhongDe Waste Technology AG signed contract to sell Beijing Miyun manufacturing site
Details
28 November 2013
ZhongDe Waste Technology AG: Weak business development despite increased order backlog
Details
28 August 2013
ZhongDe Waste Technology AG: Improved but still weak financial resultsin H1 2013 despite increased order backlog
Details
28 June 2013
ZhongDe Waste Technology AG signs EPC contract for new energy-from-waste plant in Wuhai
Details
28 May 2013
ZhongDe Waste Technology AG: First quarter 2013 shows improved year-on-year results
Details
29 April 2013
ZhongDe Waste Technology AG: Challenging circumstances adversely affect results 2012
Details
30 November 2012
ZhongDe Waste Technology AG: Financial results benefit from positive one-off effects in the third quarter 2012
Details
23 October 2012
ZhongDe Waste Technology signs BOT contract for largest waste-to-energy plant in China
Details
30 August 2012
ZhongDe Waste Technology AG: Financial results impacted by further project delays
Details
30 November 2011
ZhongDe Waste Technology AG: Revenues and gross profit improve while EBIT and net profit decline
Details
14 September 2011
ZhongDe Waste Technology AG relocates legal domicile from Hamburg to Frankfurt
Details
26 May 2011
ZhongDe Waste Technology AG: State Council of China strengthens municipal waste treatment industry
Details
2 May 2011
ZhongDe Waste Technology AG: Strong order backlog, equity and cash position despite slight net loss in 2010
Details
24 February 2011
ZhongDe Waste Technology AG: Final gross profit rate of Datong EPC project of 26.6%
Details
30 December 2010
ZhongDe Waste Technology AG: Completion of Feicheng project construction
Details
30 November 2010
ZhongDe Waste Technology AG: Strong order backlog and cash position despite revenue decrease
Details
19 November 2010
ZhongDe Waste Technology AG: Change in Supervisory Board
Details
10 November 2010
ZhongDe Waste Technology AG signed financial leasing contracts of two BOT projects
Details
30 August 2010
ZhongDe Waste Technology AG: Better Performance of Q2 2010 vs. Q2 2009
Details
27 August 2010
ZhongDe Waste Technology AG: BNY Mellon has been appointed as Depositary Bank for ADR program
Details
19 July 2010
ZhongDe Waste Technology AG moves Offices from Hamburg
to Frankfurt am Main
Details
4 June 2010
ZhongDe Waste Technology AG signs EPC contract with Shouguang Fuyuan Waste to Power Co., Ltd
Details
28 May 2010
ZhongDe Waste Technology AG: Weak Q1 financials due to difficult weather and market conditions
Details
30 April 2010
ZhongDe Waste Technology AG: Strong order backlog after strategic shift
Details
12 February 2010
ZhongDe Waste Technology AG: Successful operation of Datong Project
Details
30 December 2009
ZhongDe Waste Technology AG signs agreement to increase contract amount of Datong Project
Details
30 December 2009
ZhongDe Waste Technology AG signs EPC contract with Dingzhou Ruiquan Solid Waste Treatment Co., Ltd
Details
30 November 2009
ZhongDe Waste Technology AG presents its financial results for Q3 2009
Details
7 September 2009
ZhongDe Waste Technology AG signs Letter of Intent with Covanta Energy Asia Pacific Holdings Ltd.
Details
31 August 2009
ZhongDe Waste Technology AG adjusted strategy for future growth in 2009
Details
3 August 2009
ZhongDe Waste Technology AG Annual General Meeting adopts dividend
Details
30 July 2009
ZhongDe Waste Technology AG signs letter of intent with ThyssenKrupp Xervon Energy
Details
20 July 2009
ZhongDe Waste Technology AG signs contract for waste incineration plant in Zhaodong City
Details
10 June 2009
ZhongDe Waste Technology AG announces to postpone its Annual General Meeting
Details
29 May 2009
ZhongDe Waste Technology AG presents its financial results for Q1 2009
Details
30 April 2009
ZhongDe Waste Technology AG maintains high growth rates
Details
20 April 2009
ZhongDe Waste Technology AG announces signing of two large-size BOT projects
Details
6 April 2009
ZhongDe Waste Technology AG signs Letter of Intent on Renewable Energy Projects for Electricity Generation in Jilin, PRC
Details
3 February 2009
ZhongDe Waste Technology AG announces strategic cooperation agreement with Genesis Energy Holdings Limited
Details
23 January 2009
ZhongDe Waste Technology AG signs contract with Zhucheng Baoyuan New Energy Power Generation Co., Ltd
Details
29 December 2008
ZhongDe Waste Technology AG announces change in the Supervisory Board
Details
28 November 2008
ZhongDe Waste Technology AG reports continued healthy growth in Q3 2008
Details
10 November 2008
ZhongDe Waste Technology AG expects continuous growth and confirms initial estimation for financial year 2008
Details
30 September 2008
ZhongDe Waste Technology AG expects continuous growth and confirms initial estimation for financial year 2008
Details
29 August 2008
ZhongDe Waste Technology AG reports continuous growth in Q2 2008
Details
30 June 2008
ZhongDe Waste Technology AG announces cooperation agreement with Veolia
Details
16 June 2008
ZhongDe Waste Technology AG announces signing of Lianshui BOO project
Details
30 May 2008
ZhongDe Waste Technology AG reports strong growth in Q1 2008
Details
29 April 2008
ZhongDe Waste Technology AG presents its audited full year results for fiscal year 2007: net profit more than doubled – order intake increased by 90% to €44.4 million
Details
7 April 2008
ZhongDe Waste Technology AG announces signing of Xinjiang BOT project
Details
18 March 2008
ZhongDe Waste Technology AG releases preliminary results for fiscal year 2007: net profit more than doubled - order intake increased by 90% to €44.4 million
Details
11 March 2008
ZhongDe Waste Technology AG signs contract for large scale waste incinerator plant
Details
28 November 2007
ZhongDe Waste Technology AG continues to grow in Q3 2007
Details
19 September 2007
ZhongDe Waste Technology AG secures land usage rights in Beijing – headstone for building a second production facility
Details
28 August 2007
ZhongDe Waste Technology AG presents strong performance in H1 2007
Details
9 August 2007
ZhongDe Waste Technology AG announces signing of two BOT projects
Details
12 July 2007
ZhongDe Waste Technology AG: Greenshoe option exercised in full
Details
5 July 2007
ZhongDe Waste Technology AG sets offer price and issue volume
Details
28 June 2007
ZhongDe Waste Technology AG: Price range between Euro 23 and Euro 26
Details
25 June 2007
ZhongDe Waste Technology AG launches its Initial Public Offering on the Prime Standard in Frankfurt
Details
14 June 2007
ZhongDe Waste Technology AG planning IPO in July 2007
Details