ZhongDe Waste Technology AG: Strong order backlog, equity and cash position despite slight net loss in 2010
Frankfurt, May 02, 2011
ZhongDe Waste Technology AG ("ZhongDe", "the Company", Ticker symbol "ZEF"), a well-known player in the project development and operation of large-scale energy-from-waste plants in China, realized a net loss for the full year 2010 of EUR 0.9 million (vs. EUR 5.7 million net profit in 2009). Revenues in 2010 decreased by 16.9% to EUR 33.4 million while the EBIT regressed by 88.5% to EUR 0.9 million.
The net loss and decreased revenues in 2010 were caused by the delay in the construction progress of ZhongDe's energy-from-waste projects due to the retard of local government approvals as well as by declining revenues in the field of energy-from-waste plants. Despite the challenging circumstances, the strong order backlog, equity and cash of ZhongDe indicate the Company's potential.
Strong order backlog indicates potential revenue increase
The order backlog at the end of 2010 amounted to EUR 157.8 million, an increase of 4.4% against 2009. The backlog includes four EPC projects (Shouguang, Zhucheng, Zhaodong and Dingzhou) and four BOT projects (Feicheng, Zhoukou, Xianning and Kunming). Although more cash was invested in the construction of these projects, ZhongDe's cash position was still very strong and amounted to EUR 106.5 million. The total assets increased by 18.6% to EUR 168.6 million, while the total equity increased by 8.4% to EUR 135.6 million. "The order backlog is regarded as a strong indication of our potential to increase revenues and net profits during the coming years", says Zefeng Chen, founder and CEO of ZhongDe Waste Technology AG. Due to the strong cash position, retained earnings and optimistic forecast of ZDWT in 2011, the executive board and the supervisory board propose the distribution of a dividend of EUR 0.15 per share to the shareholders. The proposal is subject to the approval at the Annual General Meeting in June 2011.
Outlook
In 2011, the new political measures announced by the central government to support the energy-from-waste plant construction, will accelerate the approval process of the local government in China. Hence the ZhongDe management team has confidence to complete two projects (Zhoukou, Zhucheng) by the end of 2011 and three further projects (Kunming, Dingzhou and Xianning) in 2012, according to the adjusted schedule. In addition, at least one EPC project and one BOT project are going to be signed in the course of 2011. The scheduled waste disposal capacity of the new projects is not less than 1,000 tons per day, each.
Although ZhongDe performance in Q1 2011 is weak, the Company expects its sales and profit levels in 2011 and 2012 to be higher than those of 2010, because governments of China accelerates its approvals of energy-from-waste projects due to the new policies. The order backlog worth € 157.8 million as at 31 December 2010 forms the foundations of ZhongDe's growth targets. "Although we realize, that there are still risks and challenges in the future, the ZhongDe management team is confident that ZhongDe has the financial strength and expertise to keep ZhongDe's growth steady and sustainable in the new decade. We can continue to take advantage of the enormous potential in the Chinese and international energy-from-waste market and create more value for the Company and our shareholders", says Mr. Chen.
About ZhongDe Group
ZhongDe Group designs, constructs, finances and operates energy-from-waste incineration plants generating electricity from the disposal of solid municipal and industrial waste. ZhongDe realises either EPC (Engineering, Procurement and Construction) or BOT (Build, Operate and Transfer) projects, focusing on large-scale plants with waste disposal capacities of around 1,000 tons per day. Since 1996, ZhongDe Group has installed approximately 200 waste incinerators in 13 provinces and more than 80 waste incinerators in the last three financial years alone. ZhongDe is one of the leading players in the project development and operation of large-size energy-from-waste plants in China.
Contact
William Jiuhua Wang
Executive Director and CFO
E-Mail: william.jw@zhongdetech.com
Ying Sun
Assistant IR Manager
Herriotstr. 1,
60528 Frankfurt am Main
T: +49 69 67733 172
F: +49 69 67733 200
E-Mail: ying.sun@zhongde-ag.de
Kirchhoff Consult AG
Nicole Schüttforth
T: +49 40 60 91 86 64
F: +49 40 60 91 86 60
E-Mail: nicole.schuettforth@kirchhoff.de
Overview
28 November 2016
ZhongDe Wastes technology AG: Fast progress of BOT project in Lanzhou led to strongly improved revenues in the third quarter 2016
Details
30 August 2016
ZhongDe Waste Technology AG: Project in Lanzhou continues progressing rapidly
Details
27 May 2016
ZhongDe Waste Technology AG: Rapid progress of main BOT project in Lanzhou resulted in strong revenue growth
Details
29 April 2016
ZhongDe Group: Improved project progress in 2015 but earnings impacted by extraordinary effects
Details
28 August 2015
ZhongDe Waste Technology AG expects improved project progress for the second half of 2015
Details
28 May 2015
ZhongDe Waste Technology AG: Strong revenue increase reflects continuous project progress
Details
29 April 2015
ZhongDe Waste Technology AG: Remarkable project progress led to improved financial performance in 2014
Details
28 November 2014
ZhongDe Waste Technology AG: Strong year-on-year improvement of financial re-sults in the first nine months 2014
Details
28 August 2014
ZhongDe Waste Technology AG: Half-year results show slight recovery year-on-year
Details
29 April 2014
ZhongDe Waste Technology AG: Successful sale of manufacturing site led to increase in EBIT and net result
Details
23 December 2013
ZhongDe Waste Technology AG signed contract to sell Beijing Miyun manufacturing site
Details
28 November 2013
ZhongDe Waste Technology AG: Weak business development despite increased order backlog
Details
28 August 2013
ZhongDe Waste Technology AG: Improved but still weak financial resultsin H1 2013 despite increased order backlog
Details
28 June 2013
ZhongDe Waste Technology AG signs EPC contract for new energy-from-waste plant in Wuhai
Details
28 May 2013
ZhongDe Waste Technology AG: First quarter 2013 shows improved year-on-year results
Details
29 April 2013
ZhongDe Waste Technology AG: Challenging circumstances adversely affect results 2012
Details
30 November 2012
ZhongDe Waste Technology AG: Financial results benefit from positive one-off effects in the third quarter 2012
Details
23 October 2012
ZhongDe Waste Technology signs BOT contract for largest waste-to-energy plant in China
Details
30 August 2012
ZhongDe Waste Technology AG: Financial results impacted by further project delays
Details
30 November 2011
ZhongDe Waste Technology AG: Revenues and gross profit improve while EBIT and net profit decline
Details
14 September 2011
ZhongDe Waste Technology AG relocates legal domicile from Hamburg to Frankfurt
Details
26 May 2011
ZhongDe Waste Technology AG: State Council of China strengthens municipal waste treatment industry
Details
2 May 2011
ZhongDe Waste Technology AG: Strong order backlog, equity and cash position despite slight net loss in 2010
Details
24 February 2011
ZhongDe Waste Technology AG: Final gross profit rate of Datong EPC project of 26.6%
Details
30 December 2010
ZhongDe Waste Technology AG: Completion of Feicheng project construction
Details
30 November 2010
ZhongDe Waste Technology AG: Strong order backlog and cash position despite revenue decrease
Details
19 November 2010
ZhongDe Waste Technology AG: Change in Supervisory Board
Details
10 November 2010
ZhongDe Waste Technology AG signed financial leasing contracts of two BOT projects
Details
30 August 2010
ZhongDe Waste Technology AG: Better Performance of Q2 2010 vs. Q2 2009
Details
27 August 2010
ZhongDe Waste Technology AG: BNY Mellon has been appointed as Depositary Bank for ADR program
Details
19 July 2010
ZhongDe Waste Technology AG moves Offices from Hamburg
to Frankfurt am Main
Details
4 June 2010
ZhongDe Waste Technology AG signs EPC contract with Shouguang Fuyuan Waste to Power Co., Ltd
Details
28 May 2010
ZhongDe Waste Technology AG: Weak Q1 financials due to difficult weather and market conditions
Details
30 April 2010
ZhongDe Waste Technology AG: Strong order backlog after strategic shift
Details
12 February 2010
ZhongDe Waste Technology AG: Successful operation of Datong Project
Details
30 December 2009
ZhongDe Waste Technology AG signs agreement to increase contract amount of Datong Project
Details
30 December 2009
ZhongDe Waste Technology AG signs EPC contract with Dingzhou Ruiquan Solid Waste Treatment Co., Ltd
Details
30 November 2009
ZhongDe Waste Technology AG presents its financial results for Q3 2009
Details
7 September 2009
ZhongDe Waste Technology AG signs Letter of Intent with Covanta Energy Asia Pacific Holdings Ltd.
Details
31 August 2009
ZhongDe Waste Technology AG adjusted strategy for future growth in 2009
Details
3 August 2009
ZhongDe Waste Technology AG Annual General Meeting adopts dividend
Details
30 July 2009
ZhongDe Waste Technology AG signs letter of intent with ThyssenKrupp Xervon Energy
Details
20 July 2009
ZhongDe Waste Technology AG signs contract for waste incineration plant in Zhaodong City
Details
10 June 2009
ZhongDe Waste Technology AG announces to postpone its Annual General Meeting
Details
29 May 2009
ZhongDe Waste Technology AG presents its financial results for Q1 2009
Details
30 April 2009
ZhongDe Waste Technology AG maintains high growth rates
Details
20 April 2009
ZhongDe Waste Technology AG announces signing of two large-size BOT projects
Details
6 April 2009
ZhongDe Waste Technology AG signs Letter of Intent on Renewable Energy Projects for Electricity Generation in Jilin, PRC
Details
3 February 2009
ZhongDe Waste Technology AG announces strategic cooperation agreement with Genesis Energy Holdings Limited
Details
23 January 2009
ZhongDe Waste Technology AG signs contract with Zhucheng Baoyuan New Energy Power Generation Co., Ltd
Details
29 December 2008
ZhongDe Waste Technology AG announces change in the Supervisory Board
Details
28 November 2008
ZhongDe Waste Technology AG reports continued healthy growth in Q3 2008
Details
10 November 2008
ZhongDe Waste Technology AG expects continuous growth and confirms initial estimation for financial year 2008
Details
30 September 2008
ZhongDe Waste Technology AG expects continuous growth and confirms initial estimation for financial year 2008
Details
29 August 2008
ZhongDe Waste Technology AG reports continuous growth in Q2 2008
Details
30 June 2008
ZhongDe Waste Technology AG announces cooperation agreement with Veolia
Details
16 June 2008
ZhongDe Waste Technology AG announces signing of Lianshui BOO project
Details
30 May 2008
ZhongDe Waste Technology AG reports strong growth in Q1 2008
Details
29 April 2008
ZhongDe Waste Technology AG presents its audited full year results for fiscal year 2007: net profit more than doubled – order intake increased by 90% to €44.4 million
Details
7 April 2008
ZhongDe Waste Technology AG announces signing of Xinjiang BOT project
Details
18 March 2008
ZhongDe Waste Technology AG releases preliminary results for fiscal year 2007: net profit more than doubled - order intake increased by 90% to €44.4 million
Details
11 March 2008
ZhongDe Waste Technology AG signs contract for large scale waste incinerator plant
Details
28 November 2007
ZhongDe Waste Technology AG continues to grow in Q3 2007
Details
19 September 2007
ZhongDe Waste Technology AG secures land usage rights in Beijing – headstone for building a second production facility
Details
28 August 2007
ZhongDe Waste Technology AG presents strong performance in H1 2007
Details
9 August 2007
ZhongDe Waste Technology AG announces signing of two BOT projects
Details
12 July 2007
ZhongDe Waste Technology AG: Greenshoe option exercised in full
Details
5 July 2007
ZhongDe Waste Technology AG sets offer price and issue volume
Details
28 June 2007
ZhongDe Waste Technology AG: Price range between Euro 23 and Euro 26
Details
25 June 2007
ZhongDe Waste Technology AG launches its Initial Public Offering on the Prime Standard in Frankfurt
Details
14 June 2007
ZhongDe Waste Technology AG planning IPO in July 2007
Details